Isolated operation test of the power system of the Republic of Lithuania

Status: The isolated operation test was successfully completed on 22 April 2023.
 
Objective of the project
 
In preparation for synchronisation with Continental European grid, it is necessary to test the readiness of the Lithuanian energy system to operate independently.
 
Significance of the project
 
During the test, the entire Lithuanian electricity system was temporarily disconnected from the IPS/UPS synchronous zone for the first time and operated in isolated mode. Prior to the test, we checked the readiness of priority customers to work during the test, and coordinated access to the Lithuanian electricity system with transmission system operators of other countries. We also trained dispatchers and prepared IT systems for dispatch management in advance of the test.
 
Work plan
 
Activity
Date of implementation
Establishment of requirements for the assessment of priority critical network users and critical network users for the assessment of availability during isolated operation and the establishment of principles for the classification of users
1st quarter of 2022
Establishment of a list of priority critical network users and critical network users
1st quarter of 2022
Verification of the preparedness for isolated operation of priority critical network users and critical network users
4th quarter of 2022
Adaptation of an existing dispatching control system for frequency support during isolated operation tests of the Lithuanian power system
3rd quarter of 2022
Preparation and implementation of a test plan for isolated operation of the power system of the Republic of Lithuania. The test was postponed.
4th quarter of 2022
Preparation of a test plan for isolated operation of the power system of the Republic of Lithuania. 1th quarter of 2023
Implementation of a test plan for isolated operation of the power system of the Republic of Lithuania. 2th quarter of 2023
 
 
Video of the isolated work test:
 
 
Video on testing power plants: