Construction of Muša substation
Status: engineering design phase ongoing.
The aim of the project
To strengthen the electricity transmission network of Western Lithuania and ensure its reliable operation by building a 330 kV switchyard Mūša, which is important for the smooth synchronous operation of the Lithuanian electricity system with the electricity networks of continental Europe.
Significance of the project
Synchronisation with the Central European Synchronous Area (CESA)is the last step towards Lithuania’s energy independence. Currently, our electricity system is still dependent on frequency control in Russia, but already in 2025, it will operate in one synchronous area together with the systems of other European countries.
The 330 kV switchyard Mūša is one of the synchronisation projects, which will increase the reliability of supply in the Lithuanian electricity system, as well as ensure higher interconnection capacities for the electricity market with Sweden and Latvia.
Project details
|
---|
Territory: Joniškis district municipality, Gataučiai eldership. |
Voltage: 330 kV |
Area: 3.69 ha |
Estimated completion date: 2025 |
Funding: The project is co-funded by the Connecting Europe Facility (CEF). |
General project information
The Mūša switchyard project includes a 3.69 ha switchyard and 3.4 km of new power lines.
The current connection of the three T-shaped lines is not reliable enough, as their total length is as high as 182 km. This means that in the event of a fault in one place, all three lines are disconnected. The new switchyard will ensure a more reliable electricity supply in Northern Lithuania, as the longest section will be almost three times shorter than now. Currently, the connection is in the area of cultural heritage - the site of the Battle of the Sun. Therefore, the switchyard is planned to be north of this area, and power lines will be brought around the area of cultural heritage protection.
Map of the territory of 330 kV switchyard Mūša
Work calendar
Activities
|
Date of implementation
|
A contract was concluded for special spatial planning and selection for environmental impact assessment services
|
2019 Q4
|
The concept of the Development Plan was approved, which envisages alternatives for the route of electricity transmission lines and the location of the switchyard
|
2020 Q3
|
The conclusion on the environmental impact assessment of the planned economic activity was obtained
|
2020 Q4
|
Public hearings during which the residents were introduced to the solutions of the Development Plan
|
2021 Q1
|
Approval of the Development Plan
|
2021 Q3
|
Contract with the contractor for the design and construction of the switchyard
|
2022
|
Commencement of construction work
|
2023
|
Completion of project construction works
|
2025
|