Actions that must be taken in order to connect to the power transmission grid:
 
  1.  Submit an application to the electricity transmission system operator (TSO) Litgrid to issue the Preliminary Connection Specifications
    Application Form
  2. Submit an application for concluding a Letter of Intent concerning participation in auctions or reservation of power and capacities
    Application Form
  3. Submit an application to the Ministry of Energy for the issue of a permit to expand power-generating capacities
  4. Submit an application to the TSO for the issue of Connection Specifications
    Application Form
  5. Prepare and obtain agreements on the technical design and obtain a building permit
  6. Enter into a connection service agreement with the TSO
    Form of Agreement
  7. Trial operation and construction completion procedures