Actions that must be taken in order to connect to the power transmission grid:
-
Submit an application to the electricity transmission system operator (TSO) Litgrid to issue the Preliminary Connection Specifications
Application Form -
Submit an application for concluding a Letter of Intent concerning participation in auctions or reservation of power and capacities
Application Form - Submit an application to the Ministry of Energy for the issue of a permit to expand power-generating capacities
-
Submit an application to the TSO for the issue of Connection Specifications
Application Form - Prepare and obtain agreements on the technical design and obtain a building permit
-
Enter into a connection service agreement with the TSO
Form of Agreement - Trial operation and construction completion procedures