Construction of Vilnius-Neris 330 kV overhead line

Status: construction phase ongoing.
 
The aim of the project
 
To strengthen the Vilnius electricity hub by ensuring the reliability of electricity supply after synchronisation with the continental European grid and to satisfy the growing electricity demand of the capital by constructing a 330 kV electricity transmission line connecting Vilnius and Neris 330 kV transformer substations.
 
Significance of the project
 
By implementing the strategic goals of the state and reorienting the Lithuanian electricity system to work in synchronous mode with the continental European networks, reliable electricity transmission must be ensured and the security of electricity supply must be increased.
 
Synchronisation with the Central European Synchronous Area (CESA) is the last step towards Lithuania’s energy independence. Currently, our electricity system is still dependent on frequency control in Russia, but already in 2025, it will operate in one synchronous area together with the systems of other European countries.
 
After the synchronisation, the new Vilnius-Neris line is needed to ensure the reliability of electricity supply in Vilnius. It will also strengthen the Vilnius city electricity hub and create conditions for further expansion of the network to meet the growing demand of the city and district electricity.
 
Project details
Territory: Vilnius city municipality (Paneriai eldership), Vilnius district municipality (Nemenčinė, Bezdonys, Lavoriškės, Mickūnai, Šatrininkai, Rukainiai, Marijampolis, Pagiriai, Juodšiliai elderships)
Start of the planned line: Vilnius transformer substation in Paneriai eldership, J. Tiškevičiaus g. 72A
End of the planned line: Neris transformer substation in Nemenčinė eldership, Karveliškės vs., Vilijos g. 67
Total line length: 81 km
Voltage: 330 kV
Estimated completion date: 2025
Financing: The project is co-financed by the Connecting Europe Facility (CEF).
 
General project information
 
During the project, a 58 km long new line will be built from the Neris transformer substation in Nemenčinė to Marijampolis eldership, and a 23 km long section of the existing Vilnius-Molodečno overhead line from Marijampolė eldership to Vilnius transformer substation in Paneriai eldership will be reconstructed in the existing engineering corridor.  
 
Map of the planned 330 kV electricity transmission line Vilnius-Neris
 
 
 
Work calendar
 
Activities
Date of implementation
The spatial planning procedure was launched
2018 Q4
The concept of the development plan and the strategic environmental assessment (SEA) report were prepared
2019 Q4
A public hearing on the SEA report and the concept of the development plan took place and was approved in February
2020 Q1
Solutions and environmental impact assessment report (EIA) were prepared and residents in whose plots the route was planned were informed
2020 Q2
Public hearings on the EIA report and solutions
2020 Q2
Approval of the Development plan
2021 Q2
Start of design and construction works for the new line
2022
The end of works
2025