Service prices
Prices of services provided by electricity transmission system operator (TSO) Litgrid (EUR, excluding VAT)
|
|||
Transmission service prices
|
2017 | 2018 | 2019 |
Ct (EUR)
|
Ct (EUR)
|
Ct (EUR) | |
Undifferentiated transmission service price when the ownership boundary is between 330-110 kV voltage equipment, kWh
|
0,671
|
0,618
|
0,657
|
Undifferentiated transimssion service price when the ownership boundary is between 35-6 kV voltage equipment, kWh |
0,729
|
-
|
-
|
Undifferentiated system service price, kW |
0,393
|
0,529
|
0,615
|
Energy component when the ownership boundary is between 330-110 kV voltage equipment, kWh |
0,429
|
0,389
|
0,434
|
Energy component when the ownership boundary is between 35-6 kV voltage equipment, kWh |
0,468
|
0,427
|
0,477
|
“G” component (the transmission service price applied for electric energy produced and supplied to the transmission grid), kWh |
0
|
0
|
0
|
Price of entry into/exit from the network*, kWh |
0,05
|
0,05
|
0,06
|
Generation of reactive power to the transmission grid**, kVArh |
0,142
|
0,142
|
0,16
|
Use of reactive power from the transmission grid**, kVArh |
0,071
|
0,071
|
0,08
|
EUR | EUR | EUR | |
Capacity component when the ownership boundary is between 330-110 kV voltage equipment, kWh |
1,291
|
1,239
|
1,21
|
Capacity component when the ownership boundary is between 35-6 kV voltage equipment, kWh |
1,401
|
1,349
|
1,32
|
Price of system services, kW | 2,176 | 3,011 | 3,502 |
* - Price for electricity volume imported from or exported to countries, the transmission system operators of which are not parties to ITC Clearing and Settlement Multi-Year Agreement No.SUT-84-11 signed on 22 March 2011;
** - The generation/use of reactive power is paid for by distribution network operators and consumers whose electrical equipment has a permissible capacity of 30 kW or more.