NTC Belarus - Lithuania | |
NTC Lithuania - Latvia | |
Allocated capacity Latvia - Lithuania | |
NTC Lithuania - Kaliningrad | |
Allocated capacity Kaliningrad - Lithuania | |
Allocated capacity Sweden - Lithuania | |
NTC Lithuania-Sweden |
Date | NTC Belarus - Lithuania (MW) | NTC Lithuania - Latvia (MW) | Allocated capacity Latvia - Lithuania (MW) | NTC Lithuania - Kaliningrad (MW) | Allocated capacity Kaliningrad - Lithuania (MW) | Allocated capacity Sweden - Lithuania (MW) | NTC Lithuania-Sweden (MW) |
---|
2025-05-13 00:00:00 | 872.000 | 0.000 | 276.500 | 700.000 | |||
2025-05-13 01:00:00 | 858.000 | 0.000 | 477.900 | 700.000 | |||
2025-05-13 02:00:00 | 858.000 | 0.000 | 472.500 | 700.000 | |||
2025-05-13 03:00:00 | 858.000 | 0.000 | 472.200 | 700.000 | |||
2025-05-13 04:00:00 | 858.000 | 0.000 | 194.000 | 700.000 | |||
2025-05-13 05:00:00 | 858.000 | 0.000 | 400.000 | 700.000 | |||
2025-05-13 06:00:00 | 858.000 | 0.000 | 700.000 | 700.000 | |||
2025-05-13 07:00:00 | 816.000 | 0.000 | 470.300 | 700.000 | |||
2025-05-13 08:00:00 | 836.000 | 0.000 | 170.300 | 700.000 | |||
2025-05-13 09:00:00 | 845.000 | 0.000 | 0.000 | 700.000 | |||
2025-05-13 10:00:00 | 838.000 | 144.000 | 0.000 | 700.000 | |||
2025-05-13 11:00:00 | 803.000 | 0.000 | 92.500 | 700.000 | |||
2025-05-13 12:00:00 | 805.000 | 0.000 | 353.900 | 700.000 | |||
2025-05-13 13:00:00 | 816.000 | 0.000 | 448.500 | 700.000 | |||
2025-05-13 14:00:00 | 858.000 | 0.000 | 148.500 | 700.000 | |||
2025-05-13 15:00:00 | 858.000 | 23.200 | 448.500 | 700.000 | |||
2025-05-13 16:00:00 | 836.000 | 0.000 | 636.200 | 700.000 | |||
2025-05-13 17:00:00 | 813.000 | 0.000 | 675.500 | 700.000 | |||
2025-05-13 18:00:00 | 801.000 | 0.000 | 375.500 | 700.000 | |||
2025-05-13 19:00:00 | 858.000 | 0.000 | 530.300 | 700.000 | |||
2025-05-13 20:00:00 | 858.000 | 0.000 | 677.600 | 700.000 | |||
2025-05-13 21:00:00 | 858.000 | 0.000 | 636.500 | 700.000 | |||
2025-05-13 22:00:00 | 858.000 | 0.000 | 552.700 | 700.000 | |||
2025-05-13 23:00:00 | 861.000 | 0.000 | 700.000 | 700.000 |