Date | NTC Belarus - Lithuania (MW) | Allocated capacity Belarus - Lithuania (MW) | Allocated capacity Latvia - Lithuania (MW) | Allocated capacity Kaliningrad - Lithuania (MW) | Allocated capacity Lithuania - Poland (MW) | NTC Lithuania-Sweden (MW) |
---|
2025-07-03 00:00:00 | 259.600 | 193.000 | 700.000 | |||
2025-07-03 01:00:00 | 309.400 | 192.000 | 700.000 | |||
2025-07-03 02:00:00 | 338.100 | 192.000 | 700.000 | |||
2025-07-03 03:00:00 | 362.900 | 193.000 | 700.000 | |||
2025-07-03 04:00:00 | 388.900 | 193.000 | 700.000 | |||
2025-07-03 05:00:00 | 404.600 | 194.000 | 700.000 | |||
2025-07-03 06:00:00 | 267.100 | 195.000 | 700.000 | |||
2025-07-03 07:00:00 | 312.900 | 196.000 | 700.000 | |||
2025-07-03 08:00:00 | 360.900 | 195.000 | 700.000 | |||
2025-07-03 09:00:00 | 314.000 | 192.000 | 680.000 | |||
2025-07-03 10:00:00 | 273.900 | 192.000 | 650.000 | |||
2025-07-03 11:00:00 | 0.000 | 193.000 | 635.000 | |||
2025-07-03 12:00:00 | 0.000 | 195.000 | 620.000 | |||
2025-07-03 13:00:00 | 0.000 | 198.000 | 620.000 | |||
2025-07-03 14:00:00 | 0.000 | 201.000 | 635.000 | |||
2025-07-03 15:00:00 | 0.000 | 202.000 | 650.000 | |||
2025-07-03 16:00:00 | 0.000 | 204.000 | 700.000 | |||
2025-07-03 17:00:00 | 0.000 | 206.000 | 700.000 | |||
2025-07-03 18:00:00 | 0.000 | 207.000 | 700.000 | |||
2025-07-03 19:00:00 | 0.000 | 207.000 | 700.000 | |||
2025-07-03 20:00:00 | 152.200 | 208.000 | 700.000 | |||
2025-07-03 21:00:00 | 148.400 | 207.000 | 700.000 | |||
2025-07-03 22:00:00 | 248.900 | 207.000 | 700.000 | |||
2025-07-03 23:00:00 | 293.400 | 206.000 | 700.000 |