Grid development

Litgrid > Grid development > Electricity Transmission Grid Ten-Year Development Plan

Electricity Transmission Grid Ten-Year Development Plan

By implementing strategic objectives of the national power system, Litgrid prepares ten-year grid development plan on an annual basis. The plan contains forecasts of demand for electricity, power plant capacities, assessment of system adequacy, forecast of power balances for the electricity market and the system and information on the transmission grid, its development and investments.
 
The total investment in the development and reconstruction of the transmission network (including projects on the electricity network users’ initiative) for the period of 2022-2031 may amount to approximately 2.03 billion euros.
 
 
 
 
Scheme of 400-330 kV transmission grid in 2031