Steps to be taken in order to connect to the transmission grid: -
Submit an application to the transmission system operator (TSO) Litgrid and receive preliminary design conditions. Submit a request to the Ministry of Energy and receive a permit to develop generation capacities. -
Submit an application to the director of administration of a respective municipality (or an authorized municipality official) for receipt of a digest of design conditions. -
After fulfilment of requirements of Items 1, 2 and 3, to submit an application to TSO and to receive design conditions. -
Under procedure, established by legal acts, to submit to the TSO design documents and to sign an agreement with the TSO regarding a connection service. -
To submit to the National Energy Inspection a statement of verification of technical condition of electricity equipment (for transfer to tune-up work). Typical preliminary design conditions for wind power parks Typical preliminary design conditions for connection of wind parks to 110 kV grid (in Lithuanian) Map: technical possibilities of connection to the grid Map of possibilities of connection possibilities of electricity generation sources to the 330-110 kV transmission grid 
|